Delivery phases

Phase Theme Exit criterion
P0 Platform foundation Service template generates a compliant service; outbox/inbox proven
P1 Identity and master data Authenticated customer registration and catalog browsing work
P2 Onboarding saga AC-01 New Subscriber Onboarding passes end to end
P3 Revenue cycle AC-02 Billing and AC-03 Quota Exhaustion pass end to end
P4 Engagement and support Notifications dispatch on domain events; ticketing with SLA works
P5 Hardening and release NFR targets met; observability, security, K8s deployment validated
P6 Post-MVP depth (Sprints 16-23) Each sprint's own exit criteria; independently schedulable

P0-P5 are the MVP and are complete. P6 is eight independently-scoped sprints extending the platform with capabilities the MVP deliberately deferred, plus three new domain services:

Sprint Capability ADR
16 Web frontend + Web BFF (SvelteKit, Keycloak PKCE) ADR-022
17 Distributed locking (starter-lock, Redisson) ADR-024
18 Secret management (HashiCorp Vault) ADR-025
19 Service mesh and mTLS (Linkerd) ADR-026
20 Chaos engineering (Chaos Mesh) extends ADR-012/ADR-013
21 Campaign / catalog validation (campaign-service) ADR-027
22 Invoice dispute / chargeback (dispute-service) ADR-028
23 SIM-swap / fraud detection (fraud-service) ADR-029

Note: docs/product/TELCO-CRM-ADVANCED.md independently defines its own forward-looking P6-P11 enterprise themes. That is a different phase sequence that happens to share the label P6 for different content - this roadmap's P6 draws narrow, buildable slices from several of ADVANCED's themes without being equivalent to any one of them. See the roadmap's own phase-numbering note before assuming the two P6 labels mean the same thing.

Current snapshot

As of the latest STATUS.md entry, Sprints 17, 21, and 23 are fully DONE; Sprint 19 (Service Mesh and mTLS) reached full formal closure after live-cluster verification found and fixed real NetworkPolicy/mesh-routing gaps; Sprint 22 (dispute-service) is code-complete with its cross-service acceptance tests written but not yet run against a live Docker environment; Sprint 20 (Chaos Engineering) is feature-complete in authored form with its live-cluster exit criteria still open. This summary will drift - always check docs/tasks/STATUS.md directly for the current state; it is updated on every status change and carries a detailed changelog explaining exactly what was verified versus merely authored, including honest call-outs when a claimed status turned out to be wrong on re-verification.

Post-MVP candidates not yet scheduled

Tracked but with no sprint or ADR yet: prepaid top-up and real-time charging, number portability (MNP), corporate/fleet customer management, BTK regulatory reporting, roaming usage tracking, a production mobile application, and an analytics service. See the roadmap's Section 5.2 for the full list and docs/product/BRD.md Section 7.2 for the business rationale behind each deferral.

How this backlog is organized

Each sprint has its own directory under docs/tasks/sprint-NN-*/ with a README.md (scope, features table, exit criteria) and one file per feature. The per-sprint READMEs are in this site's nav under Delivery & Status > Sprints; the individual feature files are not (there are roughly 150 of them) but remain fully searchable on this site and are cross-linked extensively from their sprint's README and from STATUS.md.